Fronius Storage solutionsProduct Guide
Storage Solutions
Find out more about the compatibility of inverters and storage devices.
Fronius GEN24 Plus with BYD Battery-Box Premium HVS/HVM
The BYD Battery-Box Premium HVS/HVM is the successor of the BYD Battery Box HV. The BYD Box Premium Line is compatible with GEN24 Plus (HVS/HVM) and Symo Hybrid (HVM). The capacities of the batteries range from 5.1–10.2 kWh (HVS) and 8.3-22.1 kWh (HVM). Fronius has once again achieved true grid back-up, with the BYD Battery-Box Premium HVS/HVM. This means that even three-phase loads can be used in a grid back-up situation.
Please note:
/ During commissioning, make sure to set up the BYD using the BeConnect App first, then afterwards commission the GEN24 Plus.
/ The BYD battery should always be turned on before the inverter.
Turning the system off:
- Battery OFF: Hold the power button on the front at least 5 seconds.
- Inverter OFF: Switch off the DC-side (rotary switch on the inverter) and the AC-side (circuit breaker).
- Leave the components off for at least 30 seconds. The LEDs of the inverter and battery must be completely off.
Turning the system on:
1. Battery ON: Switch on the battery fuses. If you're unable to switch on the fuses, hold the power button for 5 seconds and try again.
2. Inverter ON: Switch on the DC-side (rotary switch on the inverter) and the AC-side (circuit breaker).
Further information on this storage solution and its backup feature can be found in the Fronius GEN24 Plus Product Guide.
Downloads
With battery management (time-of-use), rules can be defined according to which the battery is to be charged or discharged - depending on the day of the week and the time of day.
The advantages of this function:
- Individual definition of weekday and time of day dependent rules.
- Possibility for electricity tariff-dependent battery charging from the grid
- Reservation of storage capacity for the times with high PV production
Fronius Symo Hybrid with BYD Battery-Box Premium HVM
The Fronius Symo Hybrid inverter is compatible with the BYD Battery-Box Premium HVM since firmware 1.16.6-1. The firmware of the inverter can be updated on Solar.web under Settings - Components.The wiring plan for the Fronius Symo Hybrid - BYD Box Premium HVM is available in the Battery-Box Premium HVS/HVM Quick Start Guide, available in the external BYD Downloads.
Please note:
/ During commissioning, make sure to set up the BYD using the BeConnect App first, then afterwards commission the Symo Hybrid.
/ The BYD battery should always be turned on before the inverter.
Turning the system off:
- Battery OFF: Hold the power button on the front at least 5 seconds.
- Inverter OFF: Switch off the DC-side (rotary switch on the inverter) and the AC-side (circuit breaker).
- Leave the components off for at least 30 seconds. The LEDs of the inverter and battery must be completely off.
Turning the system on:
- Battery ON: Switch on the battery fuses. If you're unable to switch on the fuses, hold the power button for 5 seconds and try again.
- Inverter ON: Switch on the DC-side (rotary switch on the inverter) and the AC-side (circuit breaker).
Downloads
Backup Power
The Fronius Symo Hybrid with BYD Battery-Box Premium HVM offers a 3-phase backup power feature. The switchover from normal operation to backup power takes less than 90 seconds. A backup power switchover system is required (e.g. Enwitec switchover box). The respective version must be clarified with the grid operator.
Please note: The Fronius Symo Hybrid is a grid-connected inverter with a backup power function – it is not a stand-alone inverter. The backup power mode must not be in operation for more than 15% of the duration of the inverter's overall operating hours.